CERC Power Grid Corporation of India Limited Station Tariff Order for FY2024-25 to FY2028-29 (Case No. 597/TT/2025)
CERC order dated 6 December 2025 in Case 597/TT/2025: a 73-page station tariff order for Power Grid Corporation of India Limited, covering FY2024-25 to FY2028-29. Full section index with printed page numbers, key facts, and a link to the official order.
Key facts
- Issuing authority
- Central Electricity Regulatory Commission (CERC)
- Case number
- 597/TT/2025
- Order date
- 6 December 2025
- Petitioner
- Power Grid Corporation of India Limited (PGCIL)
- Entity
- Power Grid Corporation of India Limited (PGCIL)
- Order type
- Station Tariff Order
- Control period
- Tariff period FY2024-25 to FY2028-29
- Tariff regime
- Section 62, Electricity Act 2003
- Act sections cited
- s.62, s.79
- Licensee segment
- transmission
- Asset segment
- transmission
- State
- —
- Length
- 73 pages
About this order
A station tariff order determines the tariff of an individual generating station or transmission asset for a tariff period, based on the capital cost and operating norms in the applicable tariff regulations.
This order was issued by the Central Electricity Regulatory Commission. It relates to the control period, FY2024-25 to FY2028-29. The section index below is extracted from the order’s own structure; page numbers refer to the printed page in the official PDF.
Section index
- Backgroundp. 5
Truing up of Annual Fixed Charges for 2019-24 tariff period9 sections · p. 8
- Capital Cost for 2019-24 Tariff Periodp. 10
- Additional Capital Expenditure (ACE)p. 10
- Debt-Equity ratiop. 10
- Depreciationp. 11
- Interest on Loan (IoL)p. 11
- Return on Equity (RoE)p. 15
- Operation & Maintenance Expenses (O&M Expenses)p. 18
- Interest on Working Capital (IWC)p. 20
- Trued-up Annual Fixed Charges for 2019-24 Tariff Periodp. 21
Determination of Annual Fixed Charges for the 2024-29 Tariff Period16 sections · p. 23
- Capital Costp. 26
- Additional Capital Expenditure (ACE)p. 27
- 25. Additional Capitalisation within the original scope and after the cut-off datep. 29
- ACE Justification (item-wise replacements, Assets I & II)p. 30
- Debt-Equity ratiop. 47
- Depreciationp. 50
- Interest on Loan (IoL)p. 55
- Return on Equity (RoE)p. 57
- Operation & Maintenance Expenses (O&M Expenses)p. 60
- Interest on Working Capital (IWC)p. 63
- Annual Fixed Charges of the 2024-29 Tariff Periodp. 63
- Filing Fee and Publication Expensesp. 66
- Fees and Charges of Central Transmission Utility of India Limited (CTUIL)p. 66
- License Fee and RLDC Fees and Chargesp. 66
- Goods and Services Taxp. 66
- Security Expenses, Insurance and Capital Sparesp. 68
- Sharing of Transmission Chargesp. 70
Index extracted from the official order. Page numbers are the printed page in the PDF; front-matter (table of contents, abbreviations) is not indexed.
Ask CtrlPeriod about this order
- What did CERC decide in Case 597/TT/2025? →
- Summarise the key determinations in PGCIL’s Station Tariff Order. →
- What directions did CERC issue to PGCIL in this order? →
Related orders
- PGCIL Station Tariff Order (Case 101/TT/2025) page pending
- PGCIL Station Tariff Order (Case 192/TT/2025) page pending
- PGCIL Station Tariff Order (Case 200/TT/2025) page pending
- PGCIL Station Tariff Order (Case 202/TT/2025) page pending
- PGCIL Station Tariff Order (Case 22/TT/2025) page pending
- PGCIL Station Tariff Order (Case 221/TT/2025) page pending
- PGCIL Station Tariff Order (Case 263/TT/2025) page pending
- PGCIL Station Tariff Order (Case 267/TT/2025) page pending
- PGCIL Station Tariff Order (Case 268/TT/2025) page pending
About this page
Official order PDF (CERC) · 73 pages.
Case details, dates and the section index on this page are extracted directly from the official order published by CERC. This page was assembled by CtrlPeriod Research using automated document analysis; it does not reproduce the order’s determined tariff figures. It is a research aid, not legal or financial advice — verify against the official order before relying on it.